Bhagalpur: The renovation of the Vikramshila Setu—a vital lifeline connecting the Anga region with the Kosi and Seemanchal areas—has reached a decisive stage.
The installation of the final steel girder over the damaged sections of the bridge has been successfully completed. Immediately following this, the casting of the bridge slabs has commenced on a war footing.
The construction agency and the administration aim to have the bridge fully operational for heavy vehicles by Makar Sankranti, i.e., January 14. It is worth noting that on the night of May 3–4 of this year, a large slab near pier number 133 of the Vikramshila Setu collapsed into the Ganga River. Subsequently, a temporary Bailey bridge was installed to allow the movement of light vehicles; however, for permanent restoration, all traffic on the bridge was completely suspended starting from the night of September 30.
Under the supervision of experts brought in from various parts of the country, the team from the construction firm, SP Singla, has replaced the collapsed main section—along with three other damaged slabs—by installing steel truss girders.
According to the technical team, the slab casting work will be completed by December 15. Once the concrete is poured, it will undergo a curing process to ensure structural strength. This will be followed by ‘load testing’ to assess the bridge’s load-bearing capacity. Additionally, the old railings and footpaths are being replaced to reduce the load on the structure, and damaged expansion joints are also being repaired. The news that the bridge will become operational in January is expected to bring significant relief to lakhs of people in Bhagalpur, Naugachia, and the Seemanchal region, who currently have to take a long detour via the Shri Krishna Setu in Munger or rely on boats to cross.