Bhagalpur: Restoration and repair work on the Vikramshila Setu—a vital lifeline connecting Bhagalpur and Naugachia in North and East Bihar—is progressing on a war footing. This comes as welcome news for the millions who have faced significant commuting challenges for months. Following the installation of heavy steel girders across the four damaged sections of the bridge, the construction agency has successfully completed the laying of steel reinforcement (rebar) on three of the damaged slabs.
As part of the latest progress, the agency is now rapidly laying steel reinforcement on the girders from the Barari side; this has necessitated the cutting of specific sections of the footpath to facilitate the work. Meanwhile, on the Naugachia end, centering processes are underway, alongside the construction of the footpath and railings. The construction agency and the relevant department have set a target to complete all remaining construction and repair work by December 31.
With the steel reinforcement now in place, concrete pouring is scheduled to begin in December, starting with the section that had collapsed into the Ganga. Once the work is finished, a load test—involving a 180-tonne heavy vehicle—will be conducted to verify the structural integrity of the bridge. The administration plans to fully reopen the bridge to all traffic, including large and heavy vehicles, by January 14 (Makar Sankranti), following the completion of all necessary technical inspections.
It is worth noting that in the first week of May 2024, a technical failure near pillar number 133 caused a portion of a span to collapse into the Ganga, leading to a complete closure of the 4.7-kilometer-long bridge. Since then, commuters from Bhagalpur, Naugachia, Banka, and surrounding districts have faced significant hardship. As the repair work reaches its final stage, local traders and ordinary citizens are hopeful that traffic movement will soon be restored.